Educational Facilities

Thames Park Academy

The first Modern Methods of Construction project that DBS have undertaken.

A 6,720m² Secondary School set over three floors with a separate sports hall. Thames Park was the first Modern Methods of Construction project that DBS undertook with offsite constructions taking place at Innovare in Coventry.

DBS undertook the design and installation of the MEP services associated with the School.

Imagery © Bowmer + Kirkland

Client:ESFA
Contractor:Bowmer + Kirkland
M&E Value:£3.5 Million
Completion Date:August 2022
Mechanical Scope of Works
  • Pre-fabricated plantroom
  • LPHW heating installation
  • Domestic services installation
  • Sanitaryware installation
  • BMS controls
  • Ventilation
  • Fume and chemical extract
  • Air conditioning
  • Boiler flue
  • Thermal installation
  • Cold water storage
  • External services
  • Air and water commissioning
Electrical Scope of Works
  • Lighting and power installation
  • Structured cabling installation
  • Fire and security
  • Intruder and access control installation
  • Lightning protection
  • LV panels
  • Photovoltaics
  • Stage lighting